gridprims

Power plant · EIA plant code 10180

Metro Wastewater Reclamation District

Operator
ENGIE Denver Metro LLC
Location
Denver, CO (county level only)
Balancing authority
Public Service Company of Colorado (PSCO)
Nameplate capacity
15 MW
Summer capacity
9.8 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
36,955 MWh
Capacity factor
28.1%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
0 metric tons
Carbon dioxide per MWh
0 lb/MWh

eGRID reports 0 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Metro Wastewater Reclamation District
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Other Waste BiomassOBG2 MW1985Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
2Other Waste BiomassOBG2 MW1985Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
3Other Waste BiomassOBG2 MW1985Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
4Other Waste BiomassOBG2 MW1985Operable · As of September 2026 (EIA-860M): (SB) Standby/Backup: available for service but not normally used
5Other Waste BiomassOBG3.5 MW2000Operable · As of September 2026 (EIA-860M): (OP) Operating
6Other Waste BiomassOBG3.5 MW2000Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0