gridprims

Power plant · EIA plant code 147

Kyrene

Operator
Salt River Project
Location
Maricopa, AZ (county level only)
Balancing authority
Salt River Project (SRP)
Nameplate capacity
596.4 MW
Summer capacity
519 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
1,008,303 MWh
Capacity factor
19.3%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
480,884 metric tons
Carbon dioxide per MWh
842 lb/MWh

eGRID reports 530,083 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Kyrene
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
KY1Natural Gas Steam TurbineNG34.5 MW1952Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
KY2Natural Gas Steam TurbineNG73.5 MW1954Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
KY4Natural Gas Fired Combustion TurbineNG53.1 MW1971Operable · As of September 2026 (EIA-860M): (OP) Operating
KY5Natural Gas Fired Combustion TurbineNG60.3 MW1973Operable · As of September 2026 (EIA-860M): (OP) Operating
KY6Natural Gas Fired Combustion TurbineNG60.3 MW1973Operable · As of September 2026 (EIA-860M): (OP) Operating
KY7Natural Gas Fired Combined CycleNG192.7 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating
KY7ANatural Gas Fired Combined CycleNG122 MW2002Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0