Power plant · EIA plant code 1488
Deer Rips
- Operator
- Brookfield White Pine Hydro LLC
- Location
- Androscoggin, ME (county level only)
- Balancing authority
- ISO New England Inc. (ISNE)
- Nameplate capacity
- 6.5 MW
- Summer capacity
- 6.2 MW
U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 10, 2027. Last checked for an update: Oct 31, 2026.
Generation in 2025
- Net generation
- 50,753 MWh
- Capacity factor
- 89.1%
Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.
U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Nov 1, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 11, 2027. Last checked for an update: Nov 1, 2026.
Emissions
eGRID2023 (revision 2) reports no carbon dioxide for this plant.
Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.
U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Jan 31, 2026. Last checked for an update: Oct 31, 2026.
Generators
| Generator | Technology | Energy source | Nameplate | Operating since | Status |
|---|---|---|---|---|---|
| DR1 | Conventional Hydroelectric | WAT | 0.6 MW | 1903 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR2 | Conventional Hydroelectric | WAT | 0.6 MW | 1903 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR3 | Conventional Hydroelectric | WAT | 0.9 MW | 1906 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR4 | Conventional Hydroelectric | WAT | 0.8 MW | 1911 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR5 | Conventional Hydroelectric | WAT | 0.8 MW | 1913 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR6 | Conventional Hydroelectric | WAT | 1.8 MW | 1919 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| DR7 | Conventional Hydroelectric | WAT | 1 MW | 1924 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Nov 23, 2026. Last checked for an update: Oct 31, 2026.