gridprims

Power plant · EIA plant code 4195

Powerlane Plant

Operator
City of Greenville - (TX)
Location
Hunt, TX (county level only)
Balancing authority
Electric Reliability Council of Texas, Inc. (ERCO)
Nameplate capacity
112.2 MW
Summer capacity
106.6 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
55,775 MWh
Capacity factor
5.7%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
26,043 metric tons
Carbon dioxide per MWh
920 lb/MWh

eGRID reports 28,707 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Powerlane Plant
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
EPNatural Gas Internal Combustion EngineNG8.4 MW2010Operable · As of September 2026 (EIA-860M): (OP) Operating
EP2Natural Gas Internal Combustion EngineNG8.4 MW2010Operable · As of September 2026 (EIA-860M): (OP) Operating
EP3Natural Gas Internal Combustion EngineNG8.4 MW2010Operable · As of September 2026 (EIA-860M): (OP) Operating
ST1Natural Gas Steam TurbineNG18.8 MW1966Operable · As of September 2026 (EIA-860M): (OP) Operating
ST2Petroleum LiquidsDFO25 MW1967Operable · As of September 2026 (EIA-860M): (OP) Operating
ST3Petroleum LiquidsDFO43.2 MW1978Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem