Power plant · EIA plant code 56500
Western 102 Power Plant
- Operator
- Nevada Gold Mines
- Location
- Storey, NV (county level only)
- Balancing authority
- Nevada Power Company (NEVP)
- Nameplate capacity
- 118.6 MW
- Summer capacity
- 119.7 MW
U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 10, 2027. Last checked for an update: Oct 31, 2026.
Generation in 2025
- Net generation
- 406,176 MWh
- Capacity factor
- 39.1%
Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.
U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 11, 2027. Last checked for an update: Oct 31, 2026.
Emissions
- Carbon dioxide in 2023
- 225,820 metric tons
- Carbon dioxide per MWh
- 1,015 lb/MWh
eGRID reports 248,924 short tons. One short ton is 0.90718474 metric tons.
Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.
U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Jan 31, 2026. Last checked for an update: Oct 31, 2026.
Generators
| Generator | Technology | Energy source | Nameplate | Operating since | Status |
|---|---|---|---|---|---|
| A101 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| B102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| B202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| C102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| C202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| D101 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| E102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| E202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| F102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| F202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| G102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| G202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| H102 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| H202 | Natural Gas Internal Combustion Engine | NG | 8.4 MW | 2005 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
| PV1 | Solar Photovoltaic | SUN | 1 MW | 2007 | Operable · As of September 2026 (EIA-860M): (OP) Operating |
U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Nov 23, 2026. Last checked for an update: Oct 31, 2026.