as of Oct 27, 2026

Power plant · EIA plant code 56998

Pueblo Airport Generating Station

Operator
Black Hills Service Company LLC
Location
Pueblo, CO (county level only)
Balancing authority
Public Service Company of Colorado (PSCO)
Nameplate capacity
440 MW
Summer capacity
408 MW

Planned changes reported to EIA: 1 proposed generator.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
1,604,918 MWh
Capacity factor
41.6%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Nov 1, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
726,330 metric tons
Carbon dioxide per MWh
1,080 lb/MWh

eGRID reports 800,642 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Pueblo Airport Generating Station
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
4Natural Gas Fired Combined CycleNG40 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
43Natural Gas Fired Combined CycleNG20 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
5Natural Gas Fired Combined CycleNG40 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
53Natural Gas Fired Combined CycleNG20 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
6Natural Gas Fired Combined CycleNG40 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
7Natural Gas Fired Combined CycleNG40 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
BA7BatteriesMWH50 MWProposed, planned start 2027 · As of September 2026 (EIA-860M): (L) Regulatory approvals pending. Not under construction
CT08Natural Gas Fired Combustion TurbineNG40 MW2016Operable · As of September 2026 (EIA-860M): (OP) Operating
GT1Natural Gas Fired Combustion TurbineNG100 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating
GT2Natural Gas Fired Combustion TurbineNG100 MW2012Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem