Power plant · EIA plant code 6112

Fort St Vrain

Operator
Public Service Co of Colorado
Location
Weld, CO (county level only)
Balancing authority
Public Service Company of Colorado (PSCO)
Nameplate capacity
1,148.5 MW
Summer capacity
1,022 MW

Planned changes reported to EIA: 2 proposed generators.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
4,129,135 MWh
Capacity factor
41.0%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

Carbon dioxide in 2023
1,660,146 metric tons
Carbon dioxide per MWh
894 lb/MWh

eGRID reports 1,829,998 short tons. One short ton is 0.90718474 metric tons.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Fort St Vrain
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Natural Gas Fired Combined CycleNG342.6 MW1998Operable · As of September 2026 (EIA-860M): (OP) Operating
2Natural Gas Fired Combined CycleNG175.1 MW1996Operable · As of September 2026 (EIA-860M): (OP) Operating
3Natural Gas Fired Combined CycleNG175.1 MW1999Operable · As of September 2026 (EIA-860M): (OP) Operating
4Natural Gas Fired Combined CycleNG175.1 MW2001Operable · As of September 2026 (EIA-860M): (OP) Operating
5Natural Gas Fired Combustion TurbineNG140.3 MW2009Operable · As of September 2026 (EIA-860M): (OP) Operating
6Natural Gas Fired Combustion TurbineNG140.3 MW2009Operable · As of September 2026 (EIA-860M): (OP) Operating
7Natural Gas Fired Combustion TurbineNG239 MWProposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete
8Natural Gas Fired Combustion TurbineNG239 MWProposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0