gridprims

as of Oct 27, 2026

Power plant · EIA plant code 6440

Wilson Dam

Operator
Tennessee Valley Authority
Location
Lauderdale, AL (county level only)
Balancing authority
Tennessee Valley Authority (TVA)
Nameplate capacity
666.7 MW
Summer capacity
667.5 MW

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
2,396,274 MWh
Capacity factor
41.0%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Nov 1, 2026 · CC-BY-4.0

Emissions

eGRID2023 (revision 2) reports no carbon dioxide for this plant.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Wilson Dam
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
1Conventional HydroelectricWAT23 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
10Conventional HydroelectricWAT29.2 MW1942Operable · As of September 2026 (EIA-860M): (OP) Operating
11Conventional HydroelectricWAT29.2 MW1942Operable · As of September 2026 (EIA-860M): (OP) Operating
12Conventional HydroelectricWAT29.2 MW1942Operable · As of September 2026 (EIA-860M): (OP) Operating
13Conventional HydroelectricWAT29.2 MW1943Operable · As of September 2026 (EIA-860M): (OP) Operating
14Conventional HydroelectricWAT25.2 MW1943Operable · As of September 2026 (EIA-860M): (OP) Operating
15Conventional HydroelectricWAT29.2 MW1949Operable · As of September 2026 (EIA-860M): (OP) Operating
16Conventional HydroelectricWAT29.2 MW1950Operable · As of September 2026 (EIA-860M): (OP) Operating
17Conventional HydroelectricWAT29.2 MW1950Operable · As of September 2026 (EIA-860M): (OP) Operating
18Conventional HydroelectricWAT25.2 MW1950Operable · As of September 2026 (EIA-860M): (OP) Operating
19Conventional HydroelectricWAT54 MW1961Operable · As of September 2026 (EIA-860M): (OP) Operating
2Conventional HydroelectricWAT23 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
20Conventional HydroelectricWAT54 MW1962Operable · As of September 2026 (EIA-860M): (OP) Operating
21Conventional HydroelectricWAT54 MW1962Operable · As of September 2026 (EIA-860M): (OP) Operating
3Conventional HydroelectricWAT23 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
4Conventional HydroelectricWAT23 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
5Conventional HydroelectricWAT36 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
6Conventional HydroelectricWAT30.9 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
7Conventional HydroelectricWAT30.9 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
8Conventional HydroelectricWAT30.9 MW1925Operable · As of September 2026 (EIA-860M): (OP) Operating
9Conventional HydroelectricWAT29.2 MW1942Operable · As of September 2026 (EIA-860M): (OP) Operating

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent