Power plant · EIA plant code 69799
Project Matador Gas Plant (PMG)
- Operator
- Fermi America
- Location
- Carson, TX (county level only)
- Balancing authority
- Electric Reliability Council of Texas, Inc. (ERCO)
- Nameplate capacity
- 0 MW
- Summer capacity
- 0 MW
Planned changes reported to EIA: 157 proposed generators.
U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 10, 2027. Last checked for an update: Oct 31, 2026.
Generation in 2025
- Net generation
- Not reported
- Capacity factor
- No EIA-923 generation for 2025
Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.
U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Sep 11, 2027. Last checked for an update: Oct 31, 2026.
Emissions
This plant is not in eGRID2023 (revision 2).
U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Jan 31, 2026. Last checked for an update: Oct 31, 2026.
Generators
| Generator | Technology | Energy source | Nameplate | Operating since | Status |
|---|---|---|---|---|---|
| EG001 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG002 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG003 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG004 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG005 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG006 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG007 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG008 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG009 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG010 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG011 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG012 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG013 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG014 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG015 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG016 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG017 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG018 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG019 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG020 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG021 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG022 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG023 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG024 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG025 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG026 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG027 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG028 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG029 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG030 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG031 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG032 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG033 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG034 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG035 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG036 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG037 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG038 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG039 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG040 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG041 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG042 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG043 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG044 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG045 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG046 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG047 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| EG048 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES001 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES002 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES003 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES004 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES005 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES006 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES007 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES008 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES009 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES010 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES011 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES012 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES013 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES014 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES015 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| ES016 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1G01 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1G02 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1G03 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1S01 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1S02 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F1S03 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2G01 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2G02 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2G03 | Natural Gas Fired Combined Cycle | NG | 260 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2S01 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2S02 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| F2S03 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| FBG01 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBG02 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBG03 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBG04 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBG05 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBG06 | Natural Gas Fired Combined Cycle | NG | 50 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete | |
| FBS01 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| G6B01 | Natural Gas Fired Combustion Turbine | NG | 40 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (T) Regulatory approvals received. Not under construction | |
| G6B02 | Natural Gas Fired Combustion Turbine | NG | 40 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (T) Regulatory approvals received. Not under construction | |
| G6B03 | Natural Gas Fired Combustion Turbine | NG | 40 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (T) Regulatory approvals received. Not under construction | |
| MG001 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG002 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG003 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG004 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG005 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG006 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG007 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG008 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG009 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG010 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG011 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG012 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG013 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG014 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG015 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG016 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG017 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG018 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG019 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG020 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG021 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG022 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG023 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG024 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG025 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG026 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG027 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG028 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG029 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG030 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG031 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG032 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG033 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG034 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG035 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG036 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG037 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG038 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG039 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG040 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG041 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG042 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG043 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG044 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG045 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG046 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG047 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MG048 | Natural Gas Fired Combined Cycle | NG | 57 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS001 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS002 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS003 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS004 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS005 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS006 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS007 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS008 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS009 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS010 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS011 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS012 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS013 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS014 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS015 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| MS016 | Natural Gas Fired Combined Cycle | NG | 105 MW | Proposed, planned start 2030 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM001 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM002 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM003 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM004 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM005 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM006 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated | |
| TM007 | Natural Gas Fired Combustion Turbine | NG | 18.9 MW | Proposed, planned start 2027 · As of September 2026 (EIA-860M): (P) Planned for installation, but regulatory approvals not initiated |
U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0 May be out of date. The next release was due by Nov 23, 2026. Last checked for an update: Oct 31, 2026.