Power plant · EIA plant code 69979

MPH Elwood

Operator
MPH Elwood, LLC
Location
Will, IL (county level only)
Balancing authority
PJM Interconnection, LLC (PJM)
Nameplate capacity
1,152 MW
Summer capacity
900 MW

Planned changes reported to EIA: 4 planned retirements.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
Not reported
Capacity factor
No EIA-923 generation for 2025

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

This plant is not in eGRID2023 (revision 2).

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at MPH Elwood
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
GT1Natural Gas Fired Combustion TurbineNG192 MW1999Operable · Planned retirement: 2026 (reported to EIA) · As of September 2026 (EIA-860M): retired
GT2Natural Gas Fired Combustion TurbineNG192 MW1999Operable · Planned retirement: 2026 (reported to EIA) · As of September 2026 (EIA-860M): retired
GT3Natural Gas Fired Combustion TurbineNG192 MW1999Operable · Planned retirement: 2026 (reported to EIA) · As of September 2026 (EIA-860M): retired
GT4Natural Gas Fired Combustion TurbineNG192 MW1999Operable · Planned retirement: 2026 (reported to EIA) · As of September 2026 (EIA-860M): retired
GT8Natural Gas Fired Combustion TurbineNG192 MW2001Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year
GT9Natural Gas Fired Combustion TurbineNG192 MW2001Operable · As of September 2026 (EIA-860M): (OS) Out of service and NOT expected to return to service in next calendar year

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Report a problem

Tell us what looks wrong. The report holds only what you see in the preview below. Nothing is sent until you press Send.

Exactly what will be sent