gridprims

Power plant · EIA plant code 65072

Fremont CA AutoFactory

Operator
Tesla Inc.
Location
Alameda, CA (county level only)
Balancing authority
California Independent System Operator (CISO)
Nameplate capacity
0.3 MW
Summer capacity
0.3 MW

Planned changes reported to EIA: 4 proposed generators.

U.S. Energy Information Administration · Annual Electric Generator Report (Form EIA-860) · data for 2025 · as of Sep 10, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Generation in 2025

Net generation
524 MWh
Capacity factor
19.9%

Capacity factor is net generation divided by nameplate capacity times the hours each generator was in service that year, counted by month.

U.S. Energy Information Administration · Power Plant Operations Report (Form EIA-923) · data for 2025 · as of Sep 11, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0

Emissions

eGRID2023 (revision 2) reports no carbon dioxide for this plant.

Emissions are for 2023, the newest eGRID year. Generation is for 2025, the newest EIA-923 year.

U.S. Environmental Protection Agency · Emissions & Generation Resource Integrated Database (eGRID) · data for 2023 · as of Jun 16, 2025 · retrieved Oct 31, 2026 · CC-BY-4.0

Generators

Generators at Fremont CA AutoFactory
GeneratorTechnologyEnergy sourceNameplateOperating sinceStatus
GA3Solar PhotovoltaicSUN1.5 MWProposed, planned start 2026 · As of September 2026 (EIA-860M): (U) Under construction, less than or equal to 50 percent complete
GVSRSSolar PhotovoltaicSUN0.5 MWProposed, planned start 2026 · As of September 2026 (EIA-860M): (V) Under construction, more than 50 percent complete
RF67Solar PhotovoltaicSUN0.3 MW2022Operable · As of September 2026 (EIA-860M): (OP) Operating
STAMPSolar PhotovoltaicSUN1.4 MWProposed, planned start 2026 · As of September 2026 (EIA-860M): (TS) Construction complete, but not yet in commercial operation
VSRSSolar PhotovoltaicSUN0.4 MWProposed, planned start 2026 · As of September 2026 (EIA-860M): (TS) Construction complete, but not yet in commercial operation

U.S. Energy Information Administration · Monthly Update to the Annual Electric Generator Report (Form EIA-860M) · data for 2026-09 · as of Oct 23, 2026 · retrieved Oct 31, 2026 · CC-BY-4.0